1 Submission of application by investor
( projects proposal have been approved and got their land use certificate)
2 Examination and approval of the chosen site
Construction Planning Administration Department
Time limit: 2 working days
Management fee: 0
3 Examination of project proposal( first examination of environmental protection)
Development and Reform Bureau
Time limit: 1 working day
Management fee: 0
4 Examination and approval of land use certificate license
Development and Reform Bureau
Time limit: 3 working days
Management fee: 0
5 Approval of land use of project proposal
Land and Resources Department
Time limit: 7 working days( excluding time for provincial and municipal approval)
Management fee: land transfer charges; charges for the chang of land use rights; farmland reclamation fees; land management fees; nominal fees and service charges.
6 Examination and approval of the influence of environment
Environmental Protection Administration
Time limit: 5 working days
Management fee: expert assessment fees
7 Examination and approval of construction project license
Construction Planning Administration Department
Time limit: 5 working days
Management fee: 0
8 Issuance of construction permits
Time limit: 5 working days
Management fee: 0
Pre-approval of related industries:
1 Archaeological investigation
Culture Department
Time limit: 3 working days
Management fee: fees of investigation
2 Supervision of soil and water conservation
Time limit: 3 working days
Management fee: water conservation compensation
3 Examination and approval of of the original design
Development and Reform Bureau
Time limit: 3 working days
Management fee:expert assessment fees
4 Examination and approval of industrial safety
Production Security Administration Bureau
Time limit: 2 working days
Management fee: 0
5 Examination and approval of fire prevention and control
Fire Department
Time limit: 5 working days
Management fee: 0
6 Examination and approval of civil air defence
People Air Defence Office
Time limit: 2 working days
Management fee: 0
7 Examination and approval of prevention thunder damage
Meteorological Bureau
Time limit: 3 working days
Management fee: 0
8 Fees of projects proposal
Construction Department
A fees of urban construction
B fees of quality supervision
9 Investor
Get the approval of investigation design, project trading activity and quality security supervision.
Entrust intermediary services
Start the construction